Drywall Issues Spur Suit

Wednesday, June 1, 2016

More items for Good Technical Practice

Comment | More

The joint venture in charge of building a $1.05 billion mixed-use development in Miami has sued a drywall subcontractor for alleged substandard work.

The Americaribe and John Moriarty & Associates joint venture is seeking $2.5 million from Fort Lauderdale-based Zarrella Construction for negligence in its drywall and metal work on the Brickell City Centre, according to a local real estate news website.

Miami Downtown Brickell
© iStock.com / Roberto A Sanchez

Brickell City Centre is billed as a “new style of urban living in Miami.” The project consists of two residential towers, two office buildings, hotel and retail space, according to developers.

A copy of the lawsuit was not immediately available for review Tuesday (May 31).

Negligence Claim

The Real Deal reports that Americaribe-Moriarty filed suit in Miami-Dade Circuit Court after it found “faulty drywall and metal framework installations.”

When the issues were discovered, the suit alleges that Zarrella, which was paid nearly $7.5 million for its work, refused to rectify the issue.

The joint venture said it enlisted the help of consultants, engineers and others to “mitigate damages” and fell behind on the construction schedule as a result, the report said.

Americaribe-Moriarty also claims that the subcontractor filed a “fraudulent and exaggerated lien” on the project, the report noted.

About the Project

Brickell City Centre is billed as a “new style of urban living in Miami.” The project consists of two residential towers, two office buildings, hotel and retail space, according to the developer's website.

Officials recently announced the 500,000 square-foot retail portion of the project would be opening in November. The hotel, one of the office towers and one residential tower have already opened.

The project was designed by Arquitectonica. Its owner is Swire Properties. Turner Construction with Dragados USA were hired to complete foundation and parking phases of the project. They are not parties to the lawsuit.

Construction began in 2012 and is expected to wrap up this year.

   

Tagged categories: Commercial / Architectural; Condominiums/High-Rise Residential; Contractors; Drywall; Hotels; Lawsuits; Office Buildings; Retail; Subcontractors

Comment from Phil Kabza, (6/1/2016, 10:25 AM)

How can a sub do $1.5M of defective work without it being caught in process? No specs. No onsite quality control of subs. What do they expect? Perhaps these developers are actually fronts for law firms.


Comment from john schultz, (6/1/2016, 3:42 PM)

welcome to Miami


Comment Join the Conversation:

Sign in to our community to add your comments.

Advertisements
 
Keim Mineral Coatings
 
Mineral Silicate Paints + Stains Fuse to Concrete
 
• Forms permanent chemical bonds
• Becomes part of the concrete
• Will never peel
• Looks completely natural
 

 
Shield Industries, Inc
 
FireGuard® E-84 Intumescent Coating - Shield Industries, Inc
 
Trust the certified protection of the industry’s most innovative intumescent coating FireGuard® E-84 to provide you with the 1 and 2 hour fire ratings you need.
 

 
Novatek Corporation
 
Novatek Portable Air Filtration Systems
 
Air Scrubbers/Negative Air machines for restoration, abatement, dust & odor control, hazardous contaminant removal from job sites to clean rooms and hospitals. Portable, affordable!
 

 
 
 

Technology Publishing Co., 1501 Reedsdale Street, Suite 2008, Pittsburgh, PA 15233

TEL 1-412-431-8300  • FAX  1-412-431-5428  •  EMAIL webmaster@durabilityanddesign.com


The Technology Publishing Network

Durability + Design PaintSquare the Journal of Protective Coatings & Linings Paint BidTracker

 

© Copyright 2012-2018, Technology Publishing Co., All rights reserved